Five activities, 36 months.
From July 2026 to June 2029. Planned schedule, updated as the project progresses.
Project status
Month 5 of 36
Current phase: Preliminary studies: requirements and technical specifications
Start · 1 July 2026End · 30 June 2029
See the work plan2026202720282029
- A1Preliminary studies: requirements and technical specificationsJul 2026 – Dec 2026
- Operation concepts and use casesJul 2026 – Sep 2026
- Operational requirementsSep 2026 – Dec 2026
- Target market studyJul 2026 – Oct 2026
- A2System research and developmentJan 2027 – Nov 2028
- Feeding systemJan 2027 – Nov 2028
- Machine vision for quality control and picking pointsJan 2027 – Nov 2028
- Picking systemJan 2027 – Nov 2028
- Redistribution and rejection systemJan 2027 – Nov 2028
- Adaptive integration moduleJan 2027 – Nov 2028
- A3Integration, testing and validationFeb 2028 – Apr 2029
- Integration of subsystems into the feederFeb 2028 – Apr 2029
- Laboratory functional and performance testsMay 2028 – Apr 2029
- Shop-floor testsJul 2028 – Apr 2029
- A4Promotion, communication and disseminationJul 2026 – Jun 2029
- Project promotionJul 2026 – Jun 2029
- Technical and scientific papersFeb 2028 – Jun 2029
- National and international conferences and fairsMar 2028 – Jun 2029
- Public demonstration eventJan 2029 – Jun 2029
- A5Management and technical coordinationJul 2026 – Jun 2029
- Technical and scientific managementJul 2026 – Jun 2029
- Technology watchJul 2026 – Jun 2029
- Risk managementJul 2026 – Jun 2029
Milestones
Checkpoints.
Validation of the system functional architecture
Proofs of concept of the feeding, vision, picking, redistribution and rejection systems
First version of the flexible feeder prototype
First integrated version in the laboratory, ready for tests in a relevant environment